REPORT
OF CONCRETE CORROSION INHIBITOR TESTING
PROJECT: REPORTED
TO:
COMPARATIVE
STUDY CORTEC CORPORATION
4119 WHITE
BEAR PARKWAY
ST. PAUL
MN 55110
ATTN: BORIS
MIKSIC
AET
JOB NO: 05-00021 DATE: DECEMBER
22, 2000
INTRODUCTION
This report
presents the results of our testing of Cortecs MCI 2005, MCI
2006, and competing products. We understand the admixture was developed
to provide corrosion protection to steel embedded in concrete. Mr.
Boris Miksic of Cortec Corporation requested we evaluate the materials
effectiveness. The scope of our work consists of batching concrete;
testing plastic concrete for properties; casting, curing and testing
cylinders for compressive strength; and casting beams containing
steel and testing for corrosion.
CONCLUSIONS
Base on the
results of our work and experience, it is our opinion the following
conclusions are appropriate:
1. Cortecs
MCI 2005 and 2006 provide valuable corrosion protection for
steel embedded in concrete. The products delayed the onset of
corrosion. When corrosion developed, the products reduced the
corrosion current.
2. Cortecs
MCI 2005 and 2006 generally doubled the time to the onset of
corrosion. The control concrete developed corrosion in the 9th
test cycle. MCI 2005 developed corrosion in the 17th
test cycle and 2006 in the 28th test cycle.
3. Cortecs
MCI 2005 and 2006 reduced the corrosion current more than 5
fold once corrosion began. The control concrete corrosion current
generally increased over the 47 cycles observed with an average
corrosion current of 120 ľA. MCI 2005 average corrosion current
was 26 ľA and MCI 2006 9 ľA.
4. Cortecs
MCI 2005 and 2006 reduced the total corrosion experienced during
the test 5 to 16 fold, respectively. The average total current
passed by the control concrete was 12, 749 coulombs. MCI 2005
passed only 2803 coulombs during the test and MCI 2006 passed
only 773 coulombs.
5. Cortecs
MCI 2005 and 2006 extend the time to cracking of concrete from
rebar corrosion at least two times. The control concrete cracked
at an age of 1_ years. One beam containing MCI 2005 cracked
at about 3 years. The remaining MCI 2005 beams and all MCI 2006
beams are uncracked.
6. DCI
and Rheocrete 222 dramatically impact set time of the concrete.
The DCI accelerated initial set about 1 hour at 2 gallons and
2 hours at 4 gallons. Rheocrete 222 delayed initial set 30 minutes
and final set more than 1 hour.
7. DCI
delayed the onset of corrosion. The admixture extended the initiation
time more than four times. Corrosion began in the forth-third
cycle in the concrete with 4 gallons of DCI. Also, the corrosion
rate once established is 20% greater than the control.
- Rheocrete delayed the onset of corrosion. In the forty-sixth
cycle the corrosion current was above 10 ľA in all three beams.
- At current rates of corrosion we expect the total charge passed
in the DCI @ 4 gcy to exceed the MCI 2006 samples at the 62nd
cycle.
TESTING METHODS AND RESULTS
On July 17, 1996, and the subsequent dates, six
test batches of concrete were made at our laboratory. The batches
were 2_ cubic feet proportioned to the following mix designs:
| |
Mix 1
|
Mix 2
|
Mix 3
|
Mix 4
|
Mix 5
|
Mix 6
|
|
Portland Cement, Type I, pcy
|
600
|
600
|
600
|
600
|
600
|
600
|
|
3/4" Glacial Gravel, pcy
|
1800
|
1800
|
1800
|
1800
|
1800
|
1800
|
|
Sand, pcy
|
1130
|
1130
|
1130
|
1130
|
1130
|
1130
|
|
MCI 2005, pints/yd (liquid)
|
1.0
|
-
|
-
|
-
|
-
|
-
|
|
DCI, gal/yd
|
|
|
2
|
4
|
-
|
|
|
Rheocrete, gal/yd
|
|
|
-
|
-
|
1
|
|
|
MCI 2006, pcy (powder)
|
-
|
0.5
|
-
|
-
|
-
|
-
|
|
Neutralized Vinsol Resin, ocy
|
3.9
|
3.9
|
3.9
|
3.9
|
3.9
|
3.9
|
|
Water, pcy
|
300
|
300
|
300
|
300
|
300
|
300
|
|
Water/Cement Ratio
|
0.5
|
0.5
|
0.5
|
0.5
|
0.5
|
0.5
|
The plastic concrete was tested for slump, air
content, temperature, and unit weight immediately after discharge
into a wheelbarrow. The following data was obtained:
| |
MCI
2005
Mix #1
|
MCI
2006
Mix #2
|
DCI
2
gcy
Mix #3
|
DCI
4
gcy
Mix #4
|
Rheocrete
222
Mix #5
|
Control
Mix #6
|
|
Slump, in
|
3_
|
3_
|
3
|
3_
|
3_
|
3_
|
|
Air, %
|
6.3
|
5.8
|
5.7
|
7.0
|
5.5
|
5.7
|
|
Temp, °F
|
80
|
78
|
69
|
69
|
65
|
75
|
|
Unit Wt., lb/ft3
|
143.6
|
144.5
|
144.0
|
140.5
|
143.0
|
144.0
|
|
Set Time
Initial hr:min
Final hr:min
|
4:55
5:50
|
4:25
5:20
|
3:25
4:40
|
2:20
3:24
|
4:45
7:00
|
4:15
5:43
|
|
Compressive Strength,
psi
7 days
28 days
|
4340
5530
5200
|
3710
5960
5850
|
4430
5700
5650
|
4820
6130
5940
|
3340
4080
4180
|
3820
5520
5590
|
|
Average
|
5370
|
5900
|
5680
|
5990
|
4130
|
5560
|
Three concrete
beams were cast from each concrete batch for corrosion testing per
ASTM:G109. The beams were 4.5" x 6" x 11". Three steel reinforcing
bars were set in the form in a triangular pattern prior to casting.
The bars were taped tightly with electroplaters tape to prevent
rusting during curing. At one day the beams were stripped and moist
cured for 27 days. Upon removal from the moist room, the concrete
surface was wire brushed. The four vertical sides were sealed with
a concrete epoxy sealer. A plastic dam was positioned on top of
the beam. Silicon caulk was used to seal the dam to the beam. A
3% NaCl solution was poured into the dam for two weeks. After two
weeks of ponding, samples were dried for two weeks. This cycle was
repeated with the corrosion potential and current measured during
the middle of the ponding interval. Corrosion is considered to occur
when the macrocell current is at least 10 ľA. Tables 1-6 contain
the test data.
Report Prepared
by:
_________________________________
Tim
Suess Richard
D. Stehly, P.E.
Concrete
Engineer MN Reg.
No. 12856
|